"We are at 60 per cent of the budget" provides no meaningful insight into project status. It only becomes actionable when linked directly to how much work has actually been delivered.
The Core Problem
Traditional budget reports track consumption: planned hours versus recorded hours worked. This figure climbs predictably, yet tells you nothing about real progress.
For instance, in a project budgeted at 400 hours where 240 hours have been spent, the project may be:
- On plan, if 60 per cent of the deliverables are complete,
- Over budget, if only 40 per cent is finished,
- Under plan (ahead of schedule), if 75 per cent is complete.
Without the second metric, the first is useless.
Earned Value as a Reference Baseline
These yield two essential variance metrics:
- Cost Variance (CV): EV − AC. A negative value means: more expensive than planned.
- Schedule Variance (SV): EV − PV. A negative value means: slower than planned.
Expressing these as performance ratios: CPI = EV ÷ AC (Cost Performance Index) and SPI = EV ÷ PV (Schedule Performance Index). Values below 1.0 signal adverse deviations.
Determining the Degree of Completion Honestly
The most vulnerable element in any Earned Value calculation is estimating the percentage/degree of completion. Four common approaches include:
| Method | Description | Best Suited For |
|---|---|---|
| 0/100 Rule | Value is only recognised once the work package is 100% finished | Short work packages |
| 50/50 Rule | 50% credited upon start, remaining 50% upon full completion | Medium-sized packages |
| Milestone Method | Earned value is tied to strictly defined, verifiable deliverables | Structured, phased projects |
| Percentage Estimation | Project manager subjective estimate of completion | Last resort, prone to optimistic bias |
The first three methods are vastly superior to subjective percentage estimation because they do not rely on the self-assessment of the individuals whose project performance is being evaluated.
Practical Thresholds and Action Levels
| Level | Trigger | Action |
|---|---|---|
| Green | CPI ≥ 0.95 | None required |
| Yellow | CPI 0.85–0.95 | Project manager conducts root-cause analysis, updates regular status meeting |
| Orange | CPI 0.75–0.85 | Formal corrective action plan, alignment with client/sponsor |
| Red | CPI < 0.75 | Escalation to executive leadership; contract renegotiation, scope change, or stop |
Additionally, an absolute threshold is best practice: an automated alert upon reaching 80 per cent of total budget consumption, regardless of reported completion percentage. This catches instances where the degree of completion was overly optimistic or incorrectly estimated.
Recommended net hourly rate
56,82 €
per hour
Total billable hours: 1.056 hrs/year
Why calculate manually?
PlainStaff tracks work and project hours fully automatically, calculates mandatory breaks compliantly, and saves your business valuable hours every week.
Free trial • No credit card required
Why Daily Up-to-Date Tracking Is Decisive
Estimate to Complete vs. Linear Extrapolation
Linear extrapolation—e.g., "at 60 per cent budget spent and 40 per cent completion, we will finish at 150 per cent of budget"—is an alarm signal, not a dependable forecast. A more robust metric is the Estimate to Complete (ETC): a ground-up re-estimation of remaining required effort by the delivery team, assessed independently of past sunk hours.
Both figures should be tracked side-by-side: extrapolation indicates the statistical trajectory, while the ETC reflects direct specialist assessment. A large divergence between them is an essential finding in itself.
What Must Be Reported
A budget report packed with endless raw tables will not be read. An effective reporting format combines:
- Status via clear traffic light indicators (RAG status),
- One single figure — the projected total cost at completion (Estimate at Completion, EAC),
- One concise sentence stating the root cause of any variance,
- One corrective action with an assigned owner and firm deadline.
All supporting details and itemised breakdowns belong in the appendix.
Contractual Safeguards
For time-and-materials contracts with a budget cap (Not-to-Exceed / Capped T&M), a formal early notification duty must be stipulated in the contract: upon reaching a predefined threshold—typically 80 per cent—the service provider must issue written notice. Without such a clause, the contractor risks forfeiture of remuneration for deliverables rendered in excess of the cap.
Statutory References and Legal Framework
Accounting Standards and Valuation Principles
- UK Companies Act 2006 / FRS 102 & IAS 2 — Statutory valuation benchmarks, capitalisation rules, direct and indirect labour cost allocations, and calculation of work in progress (WIP) and project costs.
Working Time and Minimum Wage Compliance
- Working Time Regulations 1998 (WTR 1998) — Regulation 9 statutory record-keeping duties requiring employers to maintain adequate records demonstrating compliance with the 48-hour average working week limit and rest entitlements.
- National Minimum Wage Act 1998 (NMWA) — Mandatory requirements to maintain complete, contemporaneous time and payroll records for at least 6 years to prove that actual hours worked (including unbilled or overrun project hours) comply with the National Living Wage / Minimum Wage.
Audit Trail, Tax, and Data Protection Standards
- HMRC Record-Keeping & Making Tax Digital (MTD) — Statutory requirements under UK tax law to preserve immutable, digital audit trails and electronic records for a minimum of 6 years.
- UK GDPR & Data Protection Act 2018 — Requirements governing data minimization, accuracy, and storage limitation when recording employee time and performance data for project accounting.
Status of analysis: August 2026.
Frequently asked questions
- Author
- PlainStaff Editorial Team
- HR Editorial Team
- Updated on